Feasibility study of installation of booster fans, wte plant in Macomer (2010)

Modifications of existing lines, with installation of booster fans W.T.E. was ordered to deliver a feasibility study of the upgrade of booster fans allowing the discharge of combustion fumes, one fan for each line of the incineration plant with fluidised bed technology in Macomer. In the project  the new fans are placed before the existing

Feasibility study of installation of booster fans, wte plant in Macomer (2010) Read More »

Prefeasibility of the conversion of 2 EfW furnaces from fluidized bed to moving grate (2009)

Pre-feasibility study of the convertion of the combustion system installed on the incineration plant  owned by Veolia Servizi Ambientali Tecnitalia Spa in Gioia Tauro (RC). The existing fluid bed furnaces were fed with RDF and they would be transformed into moving grate furnaces fed with MSW. The capacity of the plant was 49 MWth. W.T.E.