Complete System

Design and supply for revamping of gas cleaning system in a wte plant (2011)

After a public tender W.T.E. obtained the contract for a major revamping of the MSW incineration facility. The plant was owned by AEM Gestioni Srl – Cremona, now a partner of A2A. The object of the tender was design, supply, install and start-up of: – high Dust SCR DeNOx unit, installed downstream of an exixting SNCR system –

Design and supply for revamping of gas cleaning system in a wte plant (2011) Read More »

Engineering services (2010)

W.T.E. organised a training course which would prepare the operators to the conduction of the plant. The course was focused on three items: furnace:   combustion and control of pollutant emission; maintenance combustion diagram combustion control and steam production.    

Engineering services (2010) Read More »