Consulting about malfunctioning (2017)
Terni Biomassa Srl commissioned the analysis of the combustion process to W.T.E. in order to verify the capacity of the boiler fed by RDF.
Consulting about malfunctioning (2017) Read More »
Terni Biomassa Srl commissioned the analysis of the combustion process to W.T.E. in order to verify the capacity of the boiler fed by RDF.
Consulting about malfunctioning (2017) Read More »
Preliminary thermal dimensioning of a new boiler with capacity 49 MWth fed by RDF (Refuse Derived Fuel).
Basic engineering (2016) Read More »
W.T.E. delivered preliminary engineering of a small scale Waste to Energy plant to be realised in a special urban context.
Preliminary engineering of 1,9 MWt small scale WTE plant (2013) Read More »
W.T.E. updated all operational procedures, start-up, emergency shutdown procedures, etc. for each section of the Geofor Spa Incineration plant -Ospedaletto (Pisa).
Consulting on operational procedures (2015) Read More »
The Client, Terni Biomassa Srl, appointed W.T.E. to produce a technical advice about the premature failure of the refractory lining installed in the furnace and designed to burn paper pulper residues. Serious damages on the refractory lining of the combustion chamber were observed after few months of run. Main characteristics of the boiler: steam flow
Advice about refractories premature failure (2016) Read More »
Evaluation of combustion process and control system of MSW incineration plant owned by ACEGAS-APS Spa in Trieste. The scope of work was to identify potential causes of abnormal consumption of natural gas connected to CO over production in one of three furnaces. W.T.E. studied the trend of the combustion and elaborated several energetic balances identifying
Process and control system of waste to energy plant (2012) Read More »
Basic and Detailed Engineering to adapt the steam turbine and the thermal cycle of Padua MSW incineration plant to the district heating. ACEGAS APS, owner, appointed W.T.E. to study and design the delivery of heat from the existing thermal cycle to the future district heating. The evaluation had to be done considering all existing furnaces
Basic engineering for urban district heating (2013) Read More »
ATENA, owner of the wte plant in Vercelli,  decided for a short revamping and a new start up of the incineration plant after a long inactivity period. W.T.E., who previously delivered the automatic combustion control for the three lines of incineration, was in charge of the start-up assistance and of training new operators in using
Start up and operator training of a waste to energy plant (2013) Read More »
After a public tender W.T.E. obtained the contract for a major revamping of the MSW incineration facility. The plant was owned by AEM Gestioni Srl – Cremona, now a partner of A2A. The object of the tender was design, supply, install and start-up of: – high Dust SCR DeNOx unit, installed downstream of an exixting SNCR system –
Design and supply for revamping of gas cleaning system in a wte plant (2011) Read More »
Engineering development of booster fans and related control logics in two lines, fluidized bed, of municipal solid waste Incineration plant of Macomer (NU), plant managed by TOSSILO Spa.
Engineering for gas booster fans and related control logics (2011) Read More »