ECOLOGICA NAVIGLIO Spa (2018)

Thanks to its know-how, W.T.E. was selected to deliver the study of the new control system of the existing sludge drying  plant to improve safety procedure switching from originally manual operation to an automatic one. W.T.E. also provided the related HAZOP through process analysis and management interviews. Basing on a suitable mathematical model, automation procedures were […]

GEOFOR SPA (2011)

GEOFOR Spa, owner of the incineration plant in Pisa appointed W.T.E. to study the optimization of the combustion delivering a whole control system to reduce the emission of pollutants. The plant had 2 lines, 15 MWt each, fed by MSW/RDF. The implemented logic enhances the level of quality and quantity of combustion by means of […]

VEOLIA Vercelli Energia SpA (2011)

After the start-up of the MSW incineration plant in Vercelli and some years of running, the plant management needed an additional support to optimize the combustion control system, previously delivered by W.T.E., due to the increased variability of the urban waste composition and higher heating value, caused by the spot presence of hazardous waste. Operators […]

VEOLIA- Vercelli Energia SpA (2009)

VEOLIA entrusted W.T.E. with troubleshooting the excessive CO levels in the exhaust gas, measured at the unique stack, used by three lines. The plant was owned by Vercelli Energia and managed by VEOLIA. W.T.E. designed and delivered a combustion control system, to be implemented on an existing DCS, and supplied all necessary new instruments. The […]