BEA-SPA (2025)

W.T.E. is committed to study and project a new gas recirculation system to up grade the existing the combustion control system.

Investanas JSC (2023)

Investanas JSC (Vilnius) has assigned W.T.E. Waste to Energy Srl to design a complete incineration plant, including the basic and detailed design of a furnace-boiler system (tail-end type), a flue gas cleaning system, a fly ash handling and storage system, and all other auxiliary systems. Main data: 11,5 MWth capacity 100 % MCR; LHV from […]

A.AM.P.S. SPA (2022)

Support and direct drafting of all the documents required by law in order to obtain the review of the authorisation (A.I.A. Italian document) of the operating WtE plant (expertise, review overhaul and complement of documentation, compliance with the BAT). New design of the pumping station of the water feeding system.

SIA V.L.K. (2018)

After an international public call for tender issued by Ventspils (LV) Authority, W.T.E. had assigned the job with the title: “Development of a construction design and technical specifications for the procurement of design, construction and supply of equipment within the boundaries of the project titled “Installation and Operation of a Refuse-Derived Fuel Regeneration Plant at […]

PRIMA SRL – Falck Renewables Spa (2018)

A major Italian company, operating in the field of incineration and renewable energy, required W.T.E. to study the life extension of boilers installed on an existing incineration plant. Later, the analysis was extended to the whole plant. W.T.E. carried out the study for residual useful life evaluation through an analysis of ordinary and extraordinary maintenance […]

A2A Ambiente SpA (2016)

The client, owner of the wte plant Silla2 in Milan, appointed W.T.E. to provide a solution for the treatment of the primary air, drawn from the refuse pit of the plant. WTE designed a system in two stages. A self-cleaning filter, operating as metallic sieves, was recommended. As the plant needed a deeper cleaning system […]

GEOFOR SPA (2011)

GEOFOR Spa, owner of the incineration plant in Pisa appointed W.T.E. to study the optimization of the combustion delivering a whole control system to reduce the emission of pollutants. The plant had 2 lines, 15 MWt each, fed by MSW/RDF. The implemented logic enhances the level of quality and quantity of combustion by means of […]

ATZWANGER SPA (2011)

W.T.E. was appointed to carry out expediting, quality control and engineering review for the new fired boiler, 60 MWth of capacity, to be installed on the MSW incineration plant in Bolzano. The boiler was mainly manufactured in India.

VEOLIA Vercelli Energia SpA (2011)

After the start-up of the MSW incineration plant in Vercelli and some years of running, the plant management needed an additional support to optimize the combustion control system, previously delivered by W.T.E., due to the increased variability of the urban waste composition and higher heating value, caused by the spot presence of hazardous waste. Operators […]