MASCIONI SPA (2024)

The Owner of a textile industrial firm needs a feasibility study of a new boiler and its gas cleaning system. The CHP installed and operating giving power to the production process is fed by biomass; W.T.E. was appointed to enhance the performances of the combustion and of the emissions of gases consequentlly. The study offers […]
ABET LAMINATI SPA (2021)

Feasibility study of a new co-incineration plant to be installed in the industrial area.
SIA V.L.K. (2018)

After an international public call for tender issued by Ventspils (LV) Authority, W.T.E. had assigned the job with the title: “Development of a construction design and technical specifications for the procurement of design, construction and supply of equipment within the boundaries of the project titled “Installation and Operation of a Refuse-Derived Fuel Regeneration Plant at […]
INDUNOR- Silvateam Group (2018)

Silvateam Group is an Italian holding, world leader in the production of plant base extracts, since 1854. The job assigned included the study of biomass boiler revamping to improve steam characteristics and combustion, a new thermal cycle, a new gas cleaning system and a new biomass drying system.
PRIMA SRL – Falck Renewables Spa (2018)

A major Italian company, operating in the field of incineration and renewable energy, required W.T.E. to study the life extension of boilers installed on an existing incineration plant. Later, the analysis was extended to the whole plant. W.T.E. carried out the study for residual useful life evaluation through an analysis of ordinary and extraordinary maintenance […]
VENTSPILS SILTUMS (2014)

SIA Ventspils Siltum, Multitutility of Ventspils City (Latvia) is in charge of managing the urban district heating. In 2014 Ventspils Siltum commissioned W.T.E. to carry out the technical-economic feasibility study to revamp an existing furnace-boiler, originally designed to be fed by coal following Russian technology. To reduce coal consumption W.T.E. studied the conversion to RDF […]
EDIPOWER SPA – Gruppo A2A (2013)

Feasibility study to convert a furnace, fed by diesel oil, to RDF (Refuse Derived Fuel), throughput 150 MWe. W.T.E. designed a mathematical model based on characteristics of existing boiler and suitable to describe air suspended fuel burning and energy recovery in combustion chamber. Reduced steam thermodynamic parameters were assumed in order for the boiler tubes […]
TOSSILO SPA (2010)

Modifications of existing lines, with installation of booster fans. W.T.E. was ordered to deliver a feasibility study of the upgrade of booster fans allowing the discharge of combustion fumes, one fan for each line of the incineration plant with fluidised bed technology in Macomer. In the project the new fans are placed before the existing […]